The BIG POUR

I'm sure most of you already know this, but here's the schedule for the upcoming concrete pour at the construction site across the street.

  • Monday, May 16, 7 AM to 7 PM: Concrete trucks will line up in the vicinity of 426 Alice Street while waiting to unload at the rate of about one truck every four minutes. 3rd, 4th, 5th, Harrison, Alice, and Jackson Streets will all see increased traffic and partial blocking.
  • Tuesday, May 17, 7 AM to 7 PM: Same as Monday. According to the contractor: "Please be advised that the mat pour will be split into two pours that will occur on Monday, May 16 and Tuesday May 17th. These will be all-day pours, with the largest pour on Monday." Bad weather could cause delays.

I for one am looking forward to it. Should make an interesting time-lapse! :-)